SrI:

Daer All : FYI.

V.Sadagopan

 

 

 

B. Senthil Kumar

Thursday, February 11, 2010 4:43 AM

Varadachari Sadagopan

Raw Material Requirements for Ratha Stage Construction

SrI:|Dear Swamin: adiyEn namaskArams::Kindly send this mail to your friends.Sri Nilamanagai thayar samEtha Sri Sthalasayana Perumal, Mamallapuram (Thiru Kadalmallai)1) One among 108 Divyadesams2) Birth place of Bhoodhath Azhwar3) One among Ashta vidha Sayana Divyadesams 1.Bhujanga Sayanam --- Sri Rangam (Sri Renganathar) 2.Dharpa Sayanam ------- Thirup puLLANi (Sri Ramar) 3.STHALA SAYANAM --- Thiru Kadalmallai ( Mamallapuram ) - Sri Sthalasayana Swamy 4.UththAna Sayanam ---- Thiru Kudanthai (Sri SaarngapANi Swamy) 5.Vata patra Sayanam --- Sri Villiputtur (Sri Vatapatra sayee) 6.Veera Sayanam ---------- Thiru IndhaLUr (Sri Parimala Rengan) 7.Bhoga Sayanam -------- Thiru Chitra Koodam (Chidambaram) 8.Maanicka Sayanam --- Thiru neer malai 4) Bhudhath Azhwar & Thirumangai Azhwar MangalasAsanams.5) ARTHA SETHU - equivalent to SETHU. The sea water was touched by divine hands of Sriman Narayana.Sri Nilamanagai thayar samEtha Sri Sthalasayana Perumal, Mamallapuram (Thiru Kadalmallai)The new RATHA was constructed at an estimated cost of Rs.15 Lakhs (by single donor)and ready for VeLLOttam. Now we are in the process of constructing STAGE for RATHA- THER NILAI - so that Lord could climb up and proceed during THER FESTIVAL.The Bhoomi pooja was held on 5th Feb 2010. We propose to complete the constructionwork before Chiththirai BrahmOtsavam, so that Sri Perumal could enjoy RATHA (THER)FESTIVAL during the upcoming Brahmotsavam on April 2010.The following are the raw materials to be procured for the construction with an estimatedamount:

1. Sand - 9 loads ( 1 load = Rs.4500/- )

2. Bricks - 15,000 nos. ( 1 brick = Rs.3.60 )

3. Cement - 250 bags ( 1 bag = Rs.250/- ) IRON ROD for pillars and RCC Roof

4. 12 mm Iron rod - 37 length ( Rs.15,058/- )

5. 10 mm Iron rod - 40 length ( Rs.11,400/- )

6. 8 mm Iron rod - 60 length ( Rs.10,944/- ) 7. 16 mm Iron rod - 38 length ( Rs.27,508/- )AdiyEn requests the donor(s) to select any raw materials from the above listthat they wish to contribute. Either they can send the raw materials directlyto the construction spot in Temple, Mamallapuram or they can donate the amount. For more details on contribution kindly contact adiyEn (9884364947).adiyEn,senthil.B.

Link to comment
Share on other sites

  • 1 month later...
Guest guest

SrI:

 

Dear BhakthAs of Sri Sthala Sayana PerumAl of Thirukkadanmallai ( Mahaa Balipuram) :

 

Please refer to ebook 45 in http://www.srihayagrivan.org , which deals with the Vaibhavam of Uluhu uyya PermuL of

Thirukkadanmallai eulogized by Thirumangai AzhwAr .

 

Please contact Sriman Senthilkumar ( b.senthi2002) for any support that you can give to this Kaimkaryam at Thirukkadanmallai dhivya dEsam . Thank you.

 

V.Sadagopan

 

 

 

B. Senthil Kumar

Friday, March 12, 2010 12:32 AM

Varadachari Sadagopan

Raw Material Requirements for Ratha Stage Construction

SrI:|Dear Swamin :: adiyEn namaskArams::The ratha stage construction work is going with grace of Sri Sthalasayana Perumal.adiyEn would like to intimate the status of the current progress in the work.The foundation up to plinth was completed on 10th March and the construction ofwall and pillars (4 main pillars + 4 dummy pillars) began on 11th March. The planned date for VELLOTTAM - 5th April 2010.The construction engineer planned to lay the RCC Roof and staircase on 17th or 18th March.The stage area is 16 X 16 feet, 8 pillars (4 main+4 dummy) to support the stage, stage is 10 feet height from the ground level. The portion below the stage would be used asa room for storing the RATHA materials.Through some donors so far, we had received 100 bags cement (worth Rs. 22,000) and 95% of Iron Rods (worth Rs.55,000) for the construction work. Using adiyEn's known local resources, so far paid Rs.50,000/ towards labor charge.The following are requirements for the remaining work:1. CEMENT ----------------- 100 Bags ---------------- Rs. 24,0002. SAND ------------------- 2 load ----------------------- Rs. 12,0003. BRICKS --------------- 2 load ------------------------ Rs. 20,0004. Stones 1 1/2 inch ---- 1 load -------------------- Rs. 6,0005. Stones 3/4 inch -------- 4 units ------------------ Rs. 10,0006. Weathering Tiles --- Rs. 6,000-------------------TOTAL -----------------Rs. 78,000Total Labor Charge ------------------- Rs. 1,00,000So far PAID as on 11th March --- Rs. 50,000-------Remaining to be paid------ Rs. 50,000AdiyEn requests swamin to support the construction work by contributionof RAW MATERIALS. Looking for your kind support towards RATHA STAGEconstruction for Sri Sthalasayana Swamy - Thiru Kadalmallai.adiyEn,senthil.b

Link to comment
Share on other sites

Guest guest

 

 

 

 

B. Senthil Kumar

Friday, March 12, 2010 12:32 AM

Varadachari Sadagopan

Raw Material Requirements for Ratha Stage Construction

SrI:|Dear Swamin :: adiyEn namaskArams::The ratha stage construction work is going with grace of Sri Sthalasayana Perumal.adiyEn would like to intimate the status of the current progress in the work.The foundation up to plinth was completed on 10th March and the construction ofwall and pillars (4 main pillars + 4 dummy pillars) began on 11th March. The planned date for VELLOTTAM - 5th April 2010.The construction engineer planned to lay the RCC Roof and staircase on 17th or 18th March.The stage area is 16 X 16 feet, 8 pillars (4 main+4 dummy) to support the stage, stage is 10 feet height from the ground level. The portion below the stage would be used asa room for storing the RATHA materials.Through some donors so far, we had received 100 bags cement (worth Rs. 22,000) and 95% of Iron Rods (worth Rs.55,000) for the construction work. Using adiyEn's known local resources, so far paid Rs.50,000/ towards labor charge.The following are requirements for the remaining work:1. CEMENT ----------------- 100 Bags ---------------- Rs. 24,0002. SAND ------------------- 2 load ----------------------- Rs. 12,0003. BRICKS --------------- 2 load ------------------------ Rs. 20,0004. Stones 1 1/2 inch ---- 1 load -------------------- Rs. 6,0005. Stones 3/4 inch -------- 4 units ------------------ Rs. 10,0006. Weathering Tiles --- Rs. 6,000-------------------TOTAL -----------------Rs. 78,000Total Labor Charge ------------------- Rs. 1,00,000So far PAID as on 11th March --- Rs. 50,000-------Remaining to be paid------ Rs. 50,000AdiyEn requests swamin to support the construction work by contributionof RAW MATERIALS. Looking for your kind support towards RATHA STAGEconstruction for Sri Sthalasayana Swamy - Thiru Kadalmallai.adiyEn,senthil.b

Link to comment
Share on other sites

Join the conversation

You are posting as a guest. If you have an account, sign in now to post with your account.
Note: Your post will require moderator approval before it will be visible.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

Loading...
×
×
  • Create New...